2025:757 - Bord na Móna Recreational Trail, Bunnahinly, Kilgarvan & Bloomhill Bogs, Westmeath
County: Westmeath
Site name: Bord na Móna Recreational Trail, Bunnahinly, Kilgarvan & Bloomhill Bogs
Sites and Monuments Record No.: n/a
Licence number: 25E0444 ext.
Author: Maeve McCormick
Author/Organisation Address: Archer Heritage Planning Ltd, Unit 1 Tinure Business Park, Monasterboice, Co Louth, A92 K2VF.
Site type: No archaeology found
Period/Dating: N/A
ITM: E 605560m, N 738635m
Latitude, Longitude (decimal degrees): 53.397836, -7.916399
Archaeological monitoring of groundworks got underway on sites at Bunnahinly, Kilgarvan and Bloomhill Bogs, Co. Westmeath. A desk-based assessment was undertaken by Dr. Charles Mount in October 2024 which recommended archaeological test trenching across the site. Test Excavation (25E0444) was undertaken in May 2025. Nothing of archaeological significance was recorded during the testing works. It was recommended that groundworks be monitored in the area of gateways, the parking facilities and in Testing Area 2.
Archaeological Monitoring of groundworks took place in the Gateway/Carpark area (WH-02-01) between 1 and 20 July under extension to licence 25E0444. Works are not yet complete. An interim report was submitted covering the archaeological monitoring of the Gateway/ Carpark area (WH-02-01) only. Licence was then transferred.
Works comprised the excavation of topsoil and bog to varying depths between 0.3-1.2m. Topsoil comprising a humic and root-filled silty layer which measured between 0.1-0.2m deep. The second bog layer comprised a pinkish-orange peat layer which continued beyond the depth of excavation. Subsoil was not reached in any location. Several deeper areas (up to 2m in depth) were excavated to insert drainage pipes between the Gateway/Carpark area and the drain. Works progressed in stages which comprised excavation of several meters followed by laying terram with gravel laid across the top.
No features, finds or deposits of archaeological significance were identified during the course of monitoring. Works are not complete and further monitoring will be required.